| Summary on Reconstruction and Pilot Production of Second Stage Project in Xiangguang Copper |
| Received:October 24, 2012 |
| View Full Text View/Add Comment Download reader |
| DOI:doi:10.3969/j.issn.1007-7545.2013.02.012 |
| KeyWord:copper smelting; flash smelting; reconstruction; cold repair; summary |
| Author | Institution |
| GE Zhe-ling |
祥光铜业有限公司,山东阳谷 |
|
| Hits: 2182 |
| Download times: 0 |
| Abstract: |
| The first stage 200 kt/a cathode copper project has been running for nearly four years in Xianggang Copper Co., Ltd. In 2011, the smelting system was shut down for furnace cold repair and reconstruction of the second stage 450 kt/a cathode copper project. The smelting system was put into pilot production after 50-day cold repair and reconstruction. The normal and stable operation of the second stage project marks its successful reach of the targets. The reconstruction and pilot production of this project is introduced. |