Reconstruction of Copper Recovery in Zinc Hydrometallurgy
Received:September 21, 2012   Revised:September 24, 2012   Accepted:September 25, 2012      Published Online:March 22, 2013
View Full Text  View/Add Comment  Download reader
DOI:10.3969/j.issn.1007-7545.2013.04.001
KeyWord:zinc hydrometallurgy; copper recovery; high acidity leaching; neutralization jarosite process
              
AuthorInstitution
Jiang Yan 云南省蒙自市红河学院理学院冶金系
xiaoruiming 云南省蒙自市红河学院理学院冶金系
lizijing 云南省蒙自市红河学院理学院冶金系
Sun LiDa 云南省蒙自市红河学院理学院冶金系
Huang zhushu 云南省蒙自市红河学院理学院冶金系
Hits: 2226
Download times: 2070
Abstract:
      The copper recovery of a zinc hydrometallurgy plant was low, affecting the comprehensive recovery of valuable metals. The recovery rate of copper is improved by about 20 percent point after the process transformation from “low acidity leaching, neutralization” to “two-step high acidity leaching, neutralization jarosite process”.