| Process Optimization and Practice to Treat Copper Anode Slime by Kaldo Furnace |
|
Received:June 28, 2017
Revised:June 28, 2017
Accepted:June 28, 2017
Published Online:October 31, 2017
|
| View Full Text View/Add Comment Download reader |
| DOI:doi:10.3969/j.issn.1007-7545.2017.11.004 |
| KeyWord:copper anode sludge; Kaldo Furnace; process optimization |
| Author | Institution |
| Zheng Weizhong |
紫金铜业股份有限公司 |
| Lai Shouhua |
紫金铜业股份有限公司 |
| Zhang Yongfeng |
紫金铜业股份有限公司 |
| Zhong Shuiping |
紫金铜业股份有限公司 |
| Zhang Huanran |
紫金铜业股份有限公司 |
| Liu Jianqiang |
紫金铜业股份有限公司 |
| Qiu faqiang |
紫金铜业股份有限公司 |
| Lin jiayong |
紫金铜业股份有限公司 |
|
| Hits: 2260 |
| Download times: 2335 |
| Abstract: |
| Problems existing in Kaldo Furnace operations were analyzed in terms of working model, processing capacity and equipment application. After process adjustment and equipment modification, treatment capacity of 0.8 m3 Kaldo Furnace is improved from design value of 2 000 t to 3 000 t. |